Project Status Re
Post MRM dated 31st July 2014, during the site visits by OES Team (Design & Project), it was adjudged that GIL was keen on completing the project and was working on all the presently available fronts. |
|
Site Visit dated 6th & 7th August 2014
Riser No. 18-- It is about 12 meters from the edge of the farmers land. Farmer is insisting on removal of riser from his field. Riser can be shifted outside the field, utilizing the existing tapping on the pipeline by horizontally extending the riser pipe out of his field and then making it vertical. Prima facie GIL, OES and Asset are in agreement. GIL to put up a formal proposal for acceptance.
|